Trafford Park Data Centre

Room Integrity Testing - Maintenance completed

Start: Tue, Sep 21st 2021, 08:00
End: Tue, Sep 21st 2021, 17:30

Trafford Park Data Centre
Room Integrity Testing

Tue 21st September 2021 (08:00) - Tue 21st September 2021(17:30)

Please be advised that M247 will be undertaking planned preventative maintenance checks regarding the Room Integrity of all critical rooms including Data Halls.

Room Integrity Testing works by creating pressure within the room or enclosure where the Fire Suppression System has been installed. The Test then measures the integrity of the room to ensure the gas does not dissipate too quickly before being able to extinguish the fire.

During the Room Integrity Testing, there will be periods of time where the fire suppression system will be isolated for testing purposes, however, we do not anticipate any impact on your services.

Our engineering team will be monitoring site at all times while this work is carried out.

Regards
M247 Support